Mansfield Codes Administration
Skip navigation links
.: HOME :.
.: SEARCH :.
Documents for Mansfield Borough
Mansfield Codes Administration > Inspections
Skip navigation links
Home
Documents relating to Mansfield Borough Properties only
About Us
Services
Impact of PA Act 45
Why a UCC?
PA Labor and Industry
Staff
How to find us
Municipal Members
Building Permit Process
Introduction to Obtaining a Permit
Obtaining a Permit for a New Home
Permit Process, Step-by-Step
Plan Drawing Requirements
Residential Plan Checklist
Plans Review and Issuance of Permit
Permit Fees
On-Lot Sewage System Permit
North Central Sewage Agency
SEO Coverage Areas
Water and Sewer Service
Zoning Permits
Fees and Charges Summary
Inspections
Resources
Educational
Utilities
Flood Plain Management
ADA Standards for Accessible Design
Helpful Code Hints
Downloadable Forms
Frequently Asked Questions
Links

 Inspections

Building Inspection provides enforcement of the Uniform Construction Code to ensure the minimum safety standards of building, mechanical, plumbing and electrical systems to protect residential and commercial building users.
 
A building code official shall inspect all construction for which a permit was issued.  The permit holder shall insure that the construction is accessible for inspection.  An inspection does not bar prosecution or other legal action for violation of the Uniform Construction Code.

The permit holder or an authorized agent shall notify the building code official when work is ready for inspection and provide access for the inspection.

The building code official shall notify a permit holder if construction complies with the Uniform Construction Code or fails to comply with the Uniform Construction Code.

Building Inspections Required

 

The following minimum inspections shall be required:

 

1.        Pre-permit inspection
Prior to issuance an inspection shall be conducted to ascertain compliance with the provisions of the Code. 

2.        Footing inspection.
Concrete cannot be placed before inspection approval.  Inspection will verify that forms are placed properly and on undisturbed soil as per drawings, footing are at proper depth, of proper size and to verify type of concrete to be used and placement of reinforcement.

3.        Foundation inspection
If concrete in used, Concrete cannot be placed before inspection approval.  Inspection will verify that forms are placed properly; reinforcement is in place as per the drawings. 
If Block foundation, foundation must be inspected prior to backfill. 

4.        Plumbing, mechanical and electrical inspections
Framing inspection to be made after the roof, all framing, fire blocking and bracing are in place and all pipes, chimneys and vents are complete and the rough electrical, plumbing and heating wire, pipes and ducts are approved.  These inspections can take place simultaneously.  If there is plumbing, mechanical or electrical under a slab this inspection must be done prior to the pouring of concrete.

5.        Wall board Inspection 
An inspection shall be conducted prior to taping of wallboard.

6.        Final Inspection 
To be made after finish grading and the building is completed and ready for occupancy.  Final electrical, plumbing, and mechanical inspections must be conducted prior or in conjunction with the final.

 

Other inspections

In addition to the called inspections specified above, the Code official may make or require other inspections of any construction work to ascertain compliance with the provisions of the Code. 

 

Inspection Procedure

 

Please call 570-662-2315 for scheduling of building inspections.

 

A.       Inspection request may be submitted by telephone or by contacting the Mansfield Code Administration at 19 East Wellsboro Street, Mansfield, Pa 16933

 

B.      Minimum information needed for an inspection is:

C.      Permit Number

D.      Type of Inspection

E.       Project address

F.       Contact name and phone number.

G.     The building contractor or owner is responsible for notifying the Mansfield Code Administration when inspections are required.

H.       Whenever possible, inspection requests will be done within 48 hours.  Requests for concrete inspections received before 9:00 AM may be done within 24 hours, in most cases.  Concrete inspections (footings) will take precedence.

I.          The inspection card and approved plans must be on the job site for the inspector to review.  The inspection card must be signed off prior to construction proceeding to the next phase.

J.        Final inspections or inspections related to correction notices may be scheduled for a set time by contacting the Mansfield Code Administration and requesting an appointment.  Please submit your request at least 48 hours in advance.